Hlinethaya’s 500 kV substation project 75% complete

DSC 0060 3
Union Minister for Electric Power U Nyan Tun, along with departmental officials, inspects the construction of the 500 kV Hlinethaya (Western University) substation in Yangon Region on 11 June 2024.

According to the Yangon Region Electricity Transmission and Control Department, 75 per cent of the project to build a substation with a 500 kV system has been completed in Hlinethaya Township.
Currently, the 230 kV voltage will start transmitting power this July, even though the 500 kV substation is still under construction. The entire project is scheduled to be completed by April 2025. Additionally, the installation of transformers and shunt reactors, the installation of Hybrid Gas Insulated Switchgear (HGIS), and the construction of the Control Building are also underway.
After the completion of the 500 kV Kankaung (Meiktila)-Sabakywe (Toungoo) grid, electricity will be able to be transmitted and distributed to the Yangon Region and the southern regions of Myanmar through the 230 kV Thabyaywa-Taungdwingyi and 230 kV Thabyaywa-Thazi-Shwe Myo-Pyinmana-Thaephyu-Toungoo grid via the 230 kV Thabyaywa substation. — TWA/MKKS

Share this post
Hot News
Hot News
Myanmar workers migrate illegally to Malaysia after calling visa suspension, leading them to lose properties
Chinese apples sell better than Thailand apples in Mandalay fruits market due to price gap
Myanmar and Thailand collaborate against terrorism, smuggling
30 June 2024
Myanmar joins ASEAN Committee Heads of Missions Meeting in Canberra
MoH Union Minister arrives back after attending Traditional Medicine Forum in China
Myanmar businesspeople to join Pakistan’s 16th Agri & Livestock Asia Expo in August
Former President U Thein Sein attends 70th Anniversary of Five Principle of Peaceful Coexistence in Beijing
YCC hosts International Agriculture, Energy, Food, and Hospitality Expo
Myanmar hosts 36th meeting of Myanmar-Thai Border Committee